Fig. 29.—Methods of laying distribution system: Methods 1, 2, and 3 for flat or gently sloping land; method 4 for steep slopes (see alsofig. 32);A, direction of slope;B, contour of field;C, sewer from tank, preferably size 5 inch, though 4 or 6 inch may be used, depending on the fall and the size of the siphon (see table,fig. 26);D,V-branch set to divide the flow exactly;E, reducer, to 4 inches; F, 1⁄8 bend, 4-inch;G, increaser, from 4 inches;H, increaser, 3 to 4 inches;I, reducer, 4 to 3 inches;J, distribution tile, 3-inch;K, distribution tile, 4-inch.
Fig. 29.—Methods of laying distribution system: Methods 1, 2, and 3 for flat or gently sloping land; method 4 for steep slopes (see alsofig. 32);A, direction of slope;B, contour of field;C, sewer from tank, preferably size 5 inch, though 4 or 6 inch may be used, depending on the fall and the size of the siphon (see table,fig. 26);D,V-branch set to divide the flow exactly;E, reducer, to 4 inches; F, 1⁄8 bend, 4-inch;G, increaser, from 4 inches;H, increaser, 3 to 4 inches;I, reducer, 4 to 3 inches;J, distribution tile, 3-inch;K, distribution tile, 4-inch.
The runs should be laid no deeper than necessary to give clearance when plowing and prevent injury from frost. Ten inches of earth above the top of the tile is sufficient generally throughout the southern half of the United States and 18 inches generally in the North, but if the field is exposed or lacks a thick heavy growth of grass the cover should be increased to 2½ or 3 feet near the Canadian line. What is better, the tile in all instances may be laid with a 10-inch cover and in cold weather the runs may be covered with hay, straw, or leaves weighted down, which may be removed in the spring.
Fig. 30.—Four methods of protecting open joints in distribution lines—an all-important work. Sketches show cross-section and longitudinal views; the depth from the surface of the ground to the top of the tile is about 10 inches.
Fig. 30.—Four methods of protecting open joints in distribution lines—an all-important work. Sketches show cross-section and longitudinal views; the depth from the surface of the ground to the top of the tile is about 10 inches.
1.A, Subsoil ground;B, 3 or 4 inch drain tile;C, strip of tarred paper about 6inches wide and extending three-fourths the distance around the tile, allowing sewageto escape at the bottom;D, coarse sand, gravel, broken stone or brick, slag, cinders, orcoke, the coarsest material placed around the tile (where the ground is naturally veryporous and well drained, special filling in the trench may be omitted);E, natural soil.2. Drain tile covered with a board laid flat, leaving the entire joint open.3. Drain tile laid in stoneware gutter pieces and the joint covered with stonewarecaps; gutter and cap pieces are inexpensive commercial products; their radius is longerthan that of the outside of the tile, thus leaving open most of the joint space; the gutteraids in keeping the tile in line.4. Vitrified sewer pipe with hubs facing downhill; the spigot end should be centeredin the hub with a few small chinks or wedges.
Making the joints of the distribution tile demands especial attention. For a short distance on the upper end of each run the tile should be laid with ends abutting; the joint opening should be increased gradually to one-eighth inch and this increased to one-fourth in the last 20 feet of the run. All joints should be protected against the entrance of loose dirt. Four methods are shown infigure 30. The lower end of each run should be closed with a brick or flat stone; or, what is better, an elbow orT-branch may be placed on the end and vented above the surface of the ground, improving the flow of sewage, the ventilation of pipes, and the aeration of the soil.
If the distribution tile must be laid in clay or other close, poorly drained soil, special treatment is necessary. A common method isto subsoil and underdrain the area thoroughly, as shown infigure 31. It is not always possible to run the underdrain in lines between the distribution lines as shown in figures19and31, but it is a desirable thing to do, as the sewage must then receive some filtration through natural soil.
In some instances it is sufficient to lay the distribution tile on a continuous bed, 8 to 12 inches thick, of coarse gravel, broken stone, or brick, slag, coke, or cinders and complete the refill as shown in figure18or31.
Figure 32shows two other methods of controlling the flow on steep slopes and diverting proper proportions to the several lateral distributors laid along the contour of the field. This work can not be effected properly withTorYbranches; the flow tends to shoot straight ahead, comparatively little escaping laterally. To overcome this difficulty recourse is had to diverting boxes, of which two types are shown infigure 32. These boxes involve expense, but permit inspection and division of the flow according to the needs. They may be built of brick, stone, concrete, or even wood.
Fig. 31.—Close soils should be deeply subsoiled and underdrained. Porous, well-drained, air-filled soil is absolutely necessary.A, Subsoiled ground;B, 3 or 4 inch distribution tile;C, depth variable with the climate, 1¼ to 3½ feet;D, 4-inch underdrain;E, depth such as would prepare land for good crop production, generally 3½ to 4 feet;F, stone or other coarse material;G, gravel grading upward to coarse sand;H, loose soil.
Fig. 31.—Close soils should be deeply subsoiled and underdrained. Porous, well-drained, air-filled soil is absolutely necessary.A, Subsoiled ground;B, 3 or 4 inch distribution tile;C, depth variable with the climate, 1¼ to 3½ feet;D, 4-inch underdrain;E, depth such as would prepare land for good crop production, generally 3½ to 4 feet;F, stone or other coarse material;G, gravel grading upward to coarse sand;H, loose soil.
Fig. 31.—Close soils should be deeply subsoiled and underdrained. Porous, well-drained, air-filled soil is absolutely necessary.A, Subsoiled ground;B, 3 or 4 inch distribution tile;C, depth variable with the climate, 1¼ to 3½ feet;D, 4-inch underdrain;E, depth such as would prepare land for good crop production, generally 3½ to 4 feet;F, stone or other coarse material;G, gravel grading upward to coarse sand;H, loose soil.
Type 1 consists of a single box, into which all the lateral distributors head. It will be noted that the laterals enter at slightly different elevations, the two opposite the inlet sewer being the highest, the next two slightly lower, and the next two the lowest. This staggering of the outlets, in a measure, offsets the tendency of the flow to shoot across and escape by the most direct route.
Type 2 calls for one or more diverting boxes, according to the number of lateral distributors, and readily permits of wasting sewage at widely separated elevations and distances. The outlet pipes enter the box at slightly different elevations, for the reason already stated. With either type, should the outlets not be set at the right elevations,partial plugging of the holes and a little experimenting will enable one to equalize or proportion the discharges.
Fig. 32.—Two systems of distribution on steep slopes—use of diverting box.ADirection of slope;B, contour of field;C, 4, 5 or 6 inch sewer from tank;Ddiverting box;E, 3-inch or 4-inch distribution tile.>
Fig. 32.—Two systems of distribution on steep slopes—use of diverting box.ADirection of slope;B, contour of field;C, 4, 5 or 6 inch sewer from tank;Ddiverting box;E, 3-inch or 4-inch distribution tile.>
Sewage switch.—The clogging of filters and soils after long-continued application of sewage has been previously referred to. It is, therefore, desirable to arrange the distribution system in two units with a switch between them, so that one area may drain and become aerated while the other is in use. This procedure is especially desirable where the soil is close and the installation of considerable size. It adds to the life and effectiveness of the distribution area and permits use of a plant in case it is necessary to repair, extend, or relay the tile in either unit.
Arrangement in two units does not necessarily mean doubling the amount of tile and the area required in a single field. However desirablethat may be, expense or lack of suitable ground will often prevent. With open sands and gravels and the assumed siphon dose of 20 gallons per person, 15 to 20 feet of 4-inch tile in each unit for each person will usually suffice. With more compact soil it is advisable to more nearly double the requirements previously described. Two simple types of switch are shown infigure 33. The switch should be turned frequently, certainly as often as is necessary to prevent saturation or bogginess of either area.
Fig. 33.—Two simple types of sewage switch.A, Sewer from tank;B, switch box;C, cover;D, blade or stop board (in the left-hand box the direction of flow is controlled by placing the blade in alternate diagonal position; in the right-hand box the stop works in iron guides cast integral with a short piece of light-weight pipe set in the masonry; if desired the guides may be wood, fastened to the masonry with expansion bolts);E, sewer to distribution area;F(right-hand box), alternate position of outlets or additional outlets if required.
Fig. 33.—Two simple types of sewage switch.A, Sewer from tank;B, switch box;C, cover;D, blade or stop board (in the left-hand box the direction of flow is controlled by placing the blade in alternate diagonal position; in the right-hand box the stop works in iron guides cast integral with a short piece of light-weight pipe set in the masonry; if desired the guides may be wood, fastened to the masonry with expansion bolts);E, sewer to distribution area;F(right-hand box), alternate position of outlets or additional outlets if required.
A complete installation.—The general layout and working plans of a complete installation built in 1915-16 are shown infigure 34. The plant is larger than those heretofore considered, and involves several additional features. The settling chamber below the flow line has a capacity of 1,000 gallons, and on a basis of 40 gallons per person per day would serve 25 people.
For many years sewage had been discharged through two 4-inch sewers to a cesspool in the rear of the house. The proximity of the well made it unsafe, and the overflow of the cesspool dribbled over the low portion of the garden and barnyard, creating nuisance.
The first step was to make borings with a soil auger in the pasture 400 or 500 feet from the house. The borings showed a heavy clay soil to a depth of about 4 feet, underlaid with a sandy stratum only a few inches in thickness. It was decided to locate the distribution area in the pasture and to aid the seepage of sewage by digging numerous filter wells through the clay to the sandy stratum. Levels were taken and a contour plan prepared to serve for laying out the plant and establishing the grades.
Fig. 34.—A complete installation for a large rural home. General layout on a contour plan and construction drawings. Note abandonment of old cesspool near the well and garden and removal of sewage to a lower and safer location in the pasture, where the treatment is subsurface distribution, aided by numerous filter wells about 4 feet deep filled with coarse gravel. Note that sludge is removed from the bottom of the settling chamber by opening the gate on the sludge drain.Click on image to view larger size.
Fig. 34.—A complete installation for a large rural home. General layout on a contour plan and construction drawings. Note abandonment of old cesspool near the well and garden and removal of sewage to a lower and safer location in the pasture, where the treatment is subsurface distribution, aided by numerous filter wells about 4 feet deep filled with coarse gravel. Note that sludge is removed from the bottom of the settling chamber by opening the gate on the sludge drain.Click on image to view larger size.
The septic tank is built in one corner of the barnyard, and a 5-inch sewer connects it with the old 4-inch sewers to the cesspool. All sewer pipe joints were poured with a flexible jointing compound. The settling chamber is of hopper shape at the bottom, and a 4-inch sludge drain with gate provides for the gravity removal of sludge. The lower end of the sludge drain is above the surface of the ground and 9 feet below the flow line. The end is protected by a small retaining wall, and the sludge is readily caught in barrels and hauled out on the land for burial. The outlet is low enough to drain the settling chamber completely. If it is desired merely to force out the sludge, the drain may be brought to the surface under a head of 3 to 5 feet, discharging the sludge into a trench or drying bed, to be applied later to the land. A 2-inch waste pipe about mid-depth of the settling chamber permits drawing off the clearer portion of the sewage to the siphon chamber and from thence through another 2-inch waste pipe into the 6-inch sewer leading to the distribution field.
The 4-inch siphon has a drawing depth of 33 inches, and as the siphon chamber is 4 feet wide by 6 feet long the dose is about 500 gallons. The siphon cost $35. The 6-inch sewer to the switch box falls about 6 inches in 50 feet. The distribution field was thoroughly subsoiled, and about 800 feet of 3-inch tile was laid in each unit. At intervals of 25 feet along the distribution trenches 6-inch holes were dug through the clay stratum with a posthole digger. These holes were filled with stone and constitute the filter wells previously mentioned. All tile lines are surrounded with stone and coarse gravel, and the ground has been trimmed to give a uniform cover of 12 inches. All work was done by day labor in a thorough manner. As the men were doing other work at the same time the actual cost is not known, but it is believed the installation cost about $700.
Cost data.—Reliable cost figures are difficult to estimate. Labor, materials, freight, haulage, and other items vary greatly in different localities. The septic tank shown infigure 23contains about 1,000 bricks and is estimated to cost $60 complete. The septic tank shown infigure 25for 5 persons is estimated to cost $135; for 10 persons, $170; for 15 persons, $240; for 20 persons, $280. In Maryland, in 1916, the cost of installing a septic tank similar to that shown infigure 25(for 5 people), including 86 feet of 5-inch house sewer (55 feet of cast-iron pipe passing a well, and 31 feet of vitrified pipe) and 214 feet of second-quality 4-inch sewer pipe in the distribution area, was as follows:
The quotations in the following table will be found useful in making estimates of cost:
Cost of pipe and drain tile.
(February, 1921.)
Extra heavy cast-iron soil pipe, on cars Chicago, Ill.,or Washington, D. C.
Vitrified salt-glazed sewer pipe, on cars Chicago, Ill.
Vitrified salt-glazed sewer pipe, at factory nearWashington, D. C.
Clay or shale drain tile, at factory in Ohio
Clay or shale drain tile, at factory near Washington, D. C.
The cost of cast-iron fittings may be roughly estimated as follows: Bends, one to one and one-half times the price of straight pipe;T-branches, two times the price of straight pipe; reducers, average of the prices of straight pipe at each end. The cost of clay bends,T-branches, reducers, and increasers may be roughly estimated at four times the price of straight pipe.
Operation.—Attention must be given to every plant to insure success. Unusual or excessive foulness should be investigated. No chemicals should be used in a septic tank; garbage, rags, newspaper, and other solids not readily soluble in water should be kept out of sewers and tanks. The plant should be inspected often, noting particularly if the siphon is operating satisfactorily. If scum forms in the settling chamber it should be removed, and the sludge should be bailed or pumped out yearly. Frequently tanks are not cleaned out for three or four years, resulting in large quantities of solid matter going through to the distribution system and clogging it. Clogging may occur in the tile or in the adjacent soil. In either case the tile should be dug up, cleaned, and relaid. In some cases it has been found advantageous to relay the tile between the former lines. When sewage is applied to fairly porous land at the slow rate here recommended and the plant is well handled the tile lines should operate satisfactorily for many years. Liming heavy soils tends to loosen and keep them sweet.
Field data.—As a basis for outlining or designing a suitable installation the following data should be known:
1. State, town, and whether in or near an incorporated municipality.2. Usual number of persons to be served.3. Average daily consumption of water in gallons.4. Kind and depth of well, depth to water surface.5. Character of soil, whether sandy, gravelly, loamy, clay, or muck.6. Condition of soil as to drainage.
1. State, town, and whether in or near an incorporated municipality.
2. Usual number of persons to be served.
3. Average daily consumption of water in gallons.
4. Kind and depth of well, depth to water surface.
5. Character of soil, whether sandy, gravelly, loamy, clay, or muck.
6. Condition of soil as to drainage.
7. Character of subsoil.8. Character of underlying rock and, if known, its depth below the surface.9. Depth to ground water at both house and field where sewage is to be distributed.10. Minimum winter temperature and approximate depth to which frost goes.11. Number and kind of buildings to be connected with the sewer.12. Number and kind of plumbing fixtures in each building.13. Whether plumbing fixtures are to be put in the basement.14. Depth of basement floor below ground.
7. Character of subsoil.
8. Character of underlying rock and, if known, its depth below the surface.
9. Depth to ground water at both house and field where sewage is to be distributed.
10. Minimum winter temperature and approximate depth to which frost goes.
11. Number and kind of buildings to be connected with the sewer.
12. Number and kind of plumbing fixtures in each building.
13. Whether plumbing fixtures are to be put in the basement.
14. Depth of basement floor below ground.
A plan to scale or a sketch with dimensions showing property lines, buildings, wells, springs, and drainage outlets should be furnished. The direction of surface drainage should be indicated by arrows. The slope of the land (vertical fall in a stated horizontal distance) should be given or if possible a contour plan (showing lines of constant elevation) should be furnished.