CHAPTER XIII.TIMBER BRIDGES.

Fig.79.

Fig.79.

As illustrating the very considerable stress to which cast iron may be subjected, without of necessity leading to any mishap, two cases may be cited. The first, a bridge of 32feet effective span, carrying two lines of way, each pair of rails being supported upon Barlow rails, forming the bridge floor, the ends resting upon the bottom flanges of invertedT-shaped girders, 2 feet 3 inches deep, as shown inFig. 79.

The extreme fibre stress works out at 2·9 tons per square inch in tension, and 5·9 tons per square inch compression, calculated as it would be in ordinary office work; but for the actual loads, at a span as above, exceeding the clear span by 6 inches only, and without regard to the effects of eccentric application of the load. The girders when taken out showed upon examination no sign of overstrain. The practice of loading cast-iron girders in this manner cannot, however, be too strongly condemned, notwithstanding that in this case no ill resulted. It is evident that a piece of the lower flange being broken out from this cause, as occasionally happens, might so reduce the section as to result in complete failure.

Figs.80 and 81.

Figs.80 and 81.

The second example is that of a small railway under-bridge of two spans, continuous over the central pier, each span being 16 feet 6 inches. The rails were supported upon longitudinal timbers lying within trough-shaped girders, as shown inFigs 80 and 81.

The stress over the pier, in the extreme fibres of the top flange, is estimated at 4·7 tons per square inch in tension, but it should be noted that the effect of the timber longitudinal and rail has been neglected in arriving at this result,which might possibly on this account be reduced to near 3 tons per square inch.

The case is noticeable because no evidence of high stress was apparent. The author saw nothing to suggest sinking of the central pier, the effect of which, within limits, would be to further reduce the stress as calculated; but it is quite possible some slight settlement had occurred; this, as the spans were so small, would have a sensible effect. While too much reliance should not, it is clear, be placed upon any estimated result about which there is a lingering doubt, it should be remarked that, as it would be necessary the pier should sink3⁄16of an inch, for each ton of reduced stress, it is not probable that the results quoted are in excess to any material degree; they are, indeed, more probably low, as no notice has been taken of impact.

Though cast-iron girders for railway under-bridges are now prohibited in this country for new works, there are still uses to which they may be applied, and it may be well to insist that girders of this material should be fairly loaded, theweight being brought upon them in such a way that there shall be no serious secondary stress, such as arises when wide flanges are made to carry concentrated loads; the author has, indeed, met with no instance of a cast-iron girder breaking down under a load fairly applied. Preference is now given to steel or wrought iron for columns; while this is often quite justifiable, there remain many cases in which nothing better need be desired for this purpose than good cast iron, provided only that the column be loaded in a suitable manner—i.e., axially, and that the arrangement and details of the super-structure are such that there shall be no cross-breaking efforts, or rocking of the column due to temperature or other causes; unless, indeed, such cross-breaking or rocking is definitely taken into account in designing the work. The same care observed in the detailing of cast-iron work that is not infrequently taken in the design of structures made of rolled sections would, in suitable cases, the author has no doubt, yield results just as reliable in practice, with the advantage of greater resistance to rust, and a reduced cost in maintenance.

Good cast iron is, in fact, when used with discretion, a most excellent material, popular predjudice notwithstanding. The oldest metallic bridge in this country at the present moment is of that metal.

The one chief respect in which cast iron is at a disadvantage compared with wrought iron or steel is that it does not give premonitory warning of failure—it remains intact, or it breaks. The indications of weakness, which may be read by an experienced inspector of other metallic bridges, are in a great measure absent. There is also an objection which may exist, but is to be avoided by good design and care in the foundry—viz., internal stress due to unequal cooling. In extreme cases this may lead to fracture before the workhas left the maker’s hands, but it can only occur by neglect of ordinary precautions.

Figs.82 and 83.

Figs.82 and 83.

In a case which has already been referred to in the chapter on “Deformations,”page 80, an outer rib of a cast-iron arch fractured near the crown after fifty-four years’ use. Owing to the nature of the design, and the fact that the near abutment had closed in slightly, bringing the linear arch of necessity near the lower edges of the arch segment in question, it was possible to estimate, with a probability of truth, the extreme fibre stress (tensile) due to the load forces, at the upper edge where fracture commenced. The result was very far from explaining the occurrence of the break, but an examination of the details shown inFigs. 82 and 83will make it apparent that, in addition to the tensile stress, as calculated, there was probably a severe initial stress of the same character due to irregular cooling in the foundry half a century before. The sum of these stresses, it is suggested, placed this particular casting in a critical condition, such that operations in the construction of a new bridge adjacent either by producing a small further settlement of the foundations, of which the author saw no evidence, or, as is more probable, the attachment of a rope to this rib for the purpose of keeping a barge in position, which certainly did occur, gave the arch rib just such an additional strain as to result in the break shown, though no one of these causes acting singly would have been sufficient to induce fracture. The inner ribs were of a much less objectionable section.

Fig.84.

Fig.84.

Cast-iron arches, though still allowed by the Board of Trade rules, are, indeed, liable to be seriously affected by settlement, or yielding of the abutments, unless hinges at the crown are introduced. As an instance of this may be quoted a bridge of some 45 feet span, in which the arches were cast in two pieces abutting, and very efficiently bolted together at the crown, the springing and vertical abutment member ofthe spandrel being bolted and built solidly into heavy masonry. The arch sank at the crown, caused by, or itself the cause of, a movement of the abutment, with the result that the lower bolts at the crown joint broke away, rupturing the casting, as shown inFig. 84. The arch must then have acted as though hinged at the crown, as effectiveness of the connection was destroyed. It had been better, evidently, if a proper hinge had originally been provided. The break happened to occur so as to leave a sufficiently good bearingface at the crown; there was, indeed, no tendency for one surface to slide upon another; but in the accidental fracture of cast iron this cannot be assured, and the liability to it is a risk which should be eliminated if possible.

A second case of very much the same character has also been under the author’s observation, though in this the ends of the spandrels were not built into the brickwork of which the abutments were composed. Other instances of fracture either in the arch proper or in the spandrel work, have come under notice, though particulars cannot now be adduced; but the examples cited are by themselves sufficient to justify the conclusion that it is imprudent to construct a cast-iron arch without a central pin or its equivalent, unless the abutments, being exceptionally well founded, may be relied upon as free from any liability to move. It is, however, to be borne in mind that movement in the abutments of a small arch of any given absolute amount is more injurious than the same amount of movement in the abutments of large arches of similar design, so that what may be negligible in the latter case would perhaps be destructive in the former.

To the absence of ductility and liability to initial stress must be added yet another disadvantage to which cast-iron work is prone—viz., the possibility of concealed defects, blow-holes or cold-shuts; these in good foundry practice are not very likely to occur, but, as they are possible, cannot be overlooked in considering the suitability of cast iron for bridgework, or, indeed, any structural work liable to serious stress, and particularly tensile stress. With these remarks by way of qualification, the author reiterates his opinion that there is still a use for cast iron in bridgework.

With respect to the repair of cast-iron bridges, but little is to be said; the possibilities in this direction are very limited. Occasionally it may be desired to deal with the fracture of some member in the spandrel bracing of an arch,when it is commonly sufficient, and even preferable, to limit the repair work to confining the fractured parts in such a way as to prevent displacement.

Rarely it may happen that an arch fractures as a result of settlement, or other movement, when, if it is decided that safety of the structure is not imperilled, it will in this case also be preferable to confine the parts simply by flitch-plates or other contrivance, with no attempt rigidly to make good the break, the consequences of which treatment would probably be to induce fracture in some other place. Effective strengthening of a cast-iron structure is seldom practicable, though something may occasionally be done by the negative process of lightening the dead load, or by remodelling the permanent way. Arches may, however, be rendered much more reliable by the introduction of suitable bracing where this is either wanting or inefficient.

In scheming such additions it is desirable to arrange for as little drilling of the old work as is possible; where this cannot be altogether avoided, the position of the holes should be carefully chosen with regard to the effect they may have upon the strength of the old work.

Timber bridges, though probably the most ancient in type, are yet the least durable in any particular instance. The perishable nature of the material when used for exposed construction renders it peculiarly liable to develop defects which quickly put a limit to the life of the structure. In addition to decay in the body of the main members—which may perhaps be long delayed, so that a simple beam bridge may last for many years—there is in more complex designs decay at connections and joints, which proves very detrimental to the integrity of the whole. Water running upon the surface of a member gravitates to its lower end, and, if there be a joint or other connection, settles there, to be productive of lasting mischief. From this cause, together with a very common deficiency of bearing surface relative to the forces to be met, the joints soon develop some movement; working of the structure commences under passing loads, its final destruction being then a question of time only. Each joint is, in fact, in timber bridge construction a source of serious weakness to a degree which has no parallel in well-designed metallic bridges.

Wrought-iron straps to confine the ends of raking members, or for other uses, are liable to crush into the wood, and bolts are apt to enlarge the hole through which they pass. Wood keys, where these are introduced to prevent one timber from sliding upon another, are also prone to develop cracks in the main members, and fibre crippling from excessof stress. All these defects are, however, in timber-work more easily defined than efficiently remedied, as it is barely practicable for any but the harder woods to ensure, for heavy loads, a sufficiency of bearing surfaces.

The most readily detected evidence of deterioration in timber bridges is the sag of its bearing members, or trusses, for the simple reason that if there is no local trouble at the joints, there will probably be no appreciable drop at the centre of the span. The existence of such a depression may, however, be caused in rare instances by the spread of the supporting piers or abutments, particularly in the case of beams trussed by end diagonal rakers and having no tie.

Bridges formed of deep trusses, with the road upon the top, are sometimes found to be wanting in lateral bracing, the result of which is that the main trusses go out of line, leaning considerably one way or the other, being checked only by such rigidity as the joints and floor-beam attachments may have, with possibly some assistance from the end connections of the span.

The decay of piles where entering the ground or water is, of course, a fruitful source of trouble, as also is the sinking of piles, where these are insufficient in number, or have not been well driven in the first place.

A vital difficulty with timber structures generally is the uncertainty that will commonly exist as to how far decay extends in those cases where it has started. Timber does not necessarily show upon its surface the evidences of internal rotting. Memel timber may, indeed, be sometimes found to have become thoroughly unreliable, yet showing no sign of this upon its painted surface. By sounding the wood with a hammer, or by probing, its condition may commonly be ascertained. In cases of doubt, an auger-hole will make it clear as to whether the interior be good or otherwise, asto the particular parts tested; but only as to those parts, leaving it a matter of guesswork as to the remainder.

Fig.85.

Fig.85.

A railway bridge having many of the defects which have been indicated may be quoted as an example. This structure crossed a canal, supported upon piles, some of which were in water, others carrying land spans. The canal span consisted of four trusses, one under each rail, or nearly so, framed in the manner shown inFig. 85, precise details not, however, being now available. The trusses, apart from deflection under live load, sagged considerably—in one instance, 41⁄2inches; one inside truss was also leaning towards the centre line of the bridge as much as 3 inches. One raker, or diagonal strut, was rotted half through its thickness, and many other timbers were badly decayed. The end connections and joints were also in a bad condition. The vertical tie-bolts of the main trusses were all slack. The piles generally, many of which were badly decayed, had sunk and inclined towards one end of the bridge about 4 inches in 7 feet of height, the ground being soft and unreliable.

Movement under a passenger train crawling over the bridge was very appreciable, but not startling. There had been introduced, from time to time, additional timbers and iron ties, with the object of rendering the spans more reliable, but leaving it somewhat difficult to determine the function of the several members. The bridge was, of course, reconstructed.

Fig.86.

Fig.86.

Fig.87.Fig.88.Fig.87. andFig.88.

Fig.87.Fig.88.

Fig.87. andFig.88.

An instance may here be cited showing how badly distorted a timber structure may become without actually falling. The bridge referred to consisted of three spans of 29 feet, each span having two trusses, between which ran a colliery tramroad, 1-foot 6-inch gauge; the corves running upon this, at 4 feet 6 inch centres, weighed, when full, about 10 cwt. each. The trusses were badly out of shape, the centre span having sagged 51⁄2inches, with one truss ofthe same span nearly 10 inches out of line at the centre. This little bridge, of which some details are shown inFigs. 86,87, and 88, had been in use about twenty years.

Fig.89.

Fig.89.

A third case which may be named is that of a road bridge, about 12 feet wide, crossing by thirteen spans a shallow river liable to floods. The construction was of a simple character, as indicated inFig. 89, and consisted of piles supporting trussed beams, which had sagged in some instances over21⁄2inches. The bridge had, some years previous to the author’s inspection, been heavily repaired, many new strut and stretching pieces having been introduced, the piles also being reinforced or renewed. Five years before, a traction engine, said to weigh 5 tons, had passed across the bridge in safety; but the author noticed that a coal wagon, which, with the horse, weighed about 50 cwt., when walked slowly over set up much movement. This bridge had been in use nearly thirty years, and was very much out of line from end to end.

Though timber bridges cannot at the best be considered durable, yet, by attention to certain points in design and construction, their length of life may be materially enhanced.Every cut across the grain may be considered an element of weakness by exposing the material to quicker decay, for which reason the number of ends, or of joints, should be reduced to a minimum. An additional reason for reducing the number of joints or other connections is the liability of these to develop movement, as already stated, the yield of any one joint, being the cause of movement in others, which might, but for this, have remained close. These considerations lead to the conclusion that fewness of parts is, in timber construction, as in structural work generally, an excellent principle to observe. Mortising, elaborate scarf joints, recessing, or any cutting into the timber which is not essential, should be avoided, the simplest forms of connection being preferable, if at all suitable. If a step or butt surface is wanted for any member, it is commonly better to provide this by a cleat or other added piece, rather than by cutting into the timber butted against.

A complicated joint formed in the body of main timbers can only be renewed by renewal of the timber itself, whereas by the method indicated the joint is readily tightened, or re-made, without involving the main member. Bearingsurfaces should be ample, straps of liberal dimensions, and bolts large (with good washers), both for the sake of bearing surface in the holes, and reduction of any liability to bend under cross-stress. In trusses of the form shown inFigs. 85and86, it is desirable to introduce diagonal members in the middle bay, even though it may appear that the stiffness of the main beams is sufficient to render this unnecessary as a matter of strength, as without these there is apt to be, under rolling load, a slight distortion, leading to working of the joints and free entry of moisture. Lateral bracings should also, for much the same reasons, be introduced, even though they may not appear necessary in the new structure, with joints all close and effective.

Projecting ends of timbers should be carried out well beyond the requirement of strength or bearing, in order to ensure a liberal margin for that decay in the end fibres which commonly develops. Timbers resting upon abutments, or running into confined spaces, should be arranged for free ventilation and ready drying. Occasionally joints at the lower ends of timbers are protected by lead or zinc flashings to prevent water running into them, a method which should have some protective value. Whatever measures may be adopted, whether in the design or execution of timber bridge-work, will, however, be but little effective, if the timber itself is not good of its kind, and well seasoned.

Creosoting to be useful should be thorough and something more than skin deep. The timber itself should be well dried before treatment.

The repair of timber bridges very largely consists in the renewal of decaying timbers, where this is practicable, or in adding supplementary pieces where the old cannot conveniently be displaced. Joints may be tightened up by hard-wood wedges, properly secured to prevent slacking back,all bolts being also screwed up tight, perhaps some additional being introduced.

Piles standing in water, which have decayed, may be strengthened by driving other piles between the old, or on either side, but not of necessity opposite to them, and by means of waling timbers bolted to the old piles, put in a position to take load, either by the walings resting upon their tops, or being bolted to them. Piles decayed where entering solid ground may generally be strengthened by bolting on supplementary timbers to reach well above and below the decayed part, or by cutting out the bad length, introducing a new piece, and fishing the butt-joints in a proper manner. But all remedial measures have generally to be considered with reference to cost, as compared with the probable increase of life of the structure. With a bridge in an advanced state of decrepitude, such repairs may prove anything but economical, and at the best defer reconstruction but a very moderate length of time.

Masonry bridges, in which description it is intended to include structures both in stone and brick, are, when well built, amongst the most durable and long-suffering of any which come under the care of a maintenance engineer; yet when developing the faults peculiar to their kind, they may be the occasion of much anxiety, and render necessary frequent inspection, or even continuous watching.

Apart from decay of mortar or material, defects may very commonly be traced to the foundations, or to earth-slips. Sinking, when uniform, may be quite harmless, though possibly inconvenient; irregular sinking of piers or abutments is quite a different matter. It is, however, remarkable to what a degree sinking may be evident, without of necessity rendering a structure unsafe. Movement of an amount and kind which would be fatal to the connections of metallic bridgework is endured by bridges of stone or brick; not, it may be, without damage, yet with no occasion for alarm. The superstructure of metallic bridges may often, however, be restored to the true level before the mischief has become serious, whereas in the case of masonry arches this is not practicable.

Spreading of the abutments is very seldom the cause of any great injury to an arch, though it is common enough to find old and flat arches slightly down at the crown; but the contrary case of abutments closing in is not very unusual when these are high, or terminate a viaduct over a deepvalley. Such an abutment may move during or soon after construction, throwing up the crown of the end span affected; or, if the arches are very solid and heavy, the abutment may slide forward at the base, with no sensible reduction of the opening.

When a viaduct connects the two ends of a high embankment, it may happen that the end piers are not clear of the embankment slope, in which event a pier may, should the bank slip, move with it, as to that part not in solid ground; with the result, in a bad case, that it is broken across and the superstructure imperilled.

Fig.90.

Fig.90.

A case of abutment movement is illustrated inFig. 90, which represents the end arch of a masonry viaduct, one abutment of which had moved forward in the manner already referred to. From the springing upwards the arch retained its form to within a short distance of the crown, where it was forced up in the way indicated. When the movement became pronounced, heavy timber centering was introduced, with the object of preventing any mishap, the damaged portions being ultimately cut out and made good. The structure was thirty-five years old.

The practical utility of stop piers in long arched viaducts is, perhaps, rather in checking movement of the tops of piersunder moving load than in arresting actual failure of a series of arches. That the tops of piers do move very sensibly need not be doubted. The author has attempted to measure this in the case of piers about 60 feet to the springing, by means of a theodolite placed below, but has reached no more definite result than that a movement existed, of which he was not able to determine the amount. If in a viaduct some arches are more heavily loaded than others, each spreading slightly, the end piers of the group will move amounts which together equal the sum of the individual span spreads, with a tendency in the arches beyond those of the group overloaded to rise.

This rocking may be detrimental both to the piers and arches, and helps to account for the disintegration of mortar in arches and piers, which not infrequently happens. The soffits will sometimes be seen with a thick incrustation of lime, which has washed out of the joints, or from limestone ballast above, where this has been in use. Arches of tall viaducts may, indeed, become in so bad a condition that pieces of stone or brick will drop out, necessitating repair at heavy expense, of which scaffolding is commonly a large part.

Tall piers may be found badly out of the upright due to sinking of foundations. A marked case of this kind came under the author’s notice—a viaduct of fifteen semicircular arches, in which, though many piers were wanting in truth, one in particular was about 1 foot 4 inches out of vertical, making one side of the shaft plumb, and doubling the normal batter of the other. Inquiry showed that in this instance the pier had never been upright from its earliest history dating back thirty-six years. This makes clear the desirability, to avoid hasty conclusions, of ascertaining, when it is possible to do so, the complete record of any structure.

A bridge fifty-eight years old, of three skew spans, carryinga railway over a canal, and having somewhat flat brick arches with stone quoins upon low piers, developed the somewhat unusual defect, as to the centre arch, of splitting along its length for about 10 feet, parallel to and some 7 feet from one face. In this case there was reason to believe that there had been considerable local settlement of the piers on that side of the bridge. The arches were otherwise in bad condition, the brickwork poor, and the mortar decayed. Each arch was down at the centre, and displayed a fault not unusual where bad brickwork joins up to good cut stonework, the quoins showing a tendency to separate from the brick rings. Below the bridge were coal-workings.

Brick arches built in parallel rings sometimes separate one ring from the other, demonstrating the known propriety of bonding the rings together properly, and of carrying the arch round, when building, at its full thickness.

Fig.91.

Fig.91.

An instance of bridge failure from a somewhat peculiar cause may be quoted as of some interest, largely because the structure was very ancient, having been in existence some 400 years. This bridge, carrying a road, was of the type usual in old masonry bridges over a river, having small arches, thick piers, and solid backings to the arches. Twoflood-openings at one end had, by sinking and want of care, become partly closed. The centre arch had, however, been widened about 140 years previously. During a severe flood, the swollen river, overflowing its banks, trespassed upon a timber yard a little above bridge, and washed down into the stream a large quantity of sawn timber; this, unable to get through the main arch with freedom, compacted into a serious obstruction. The flood water, thus checked in its passage, seems to have scoured below the timber, and robbed the piers of such support as they formerly had (seeFig. 91). The bridge stood in this condition till the water lowered, when the middle part of the structure broke up, and subsided into the hole which had been washed out. But for the monolithic character of the old work it is probable the bridge would have failed long before, as the gravel bed on which the piers stood had been partly undermined for very many years. The case is instructive, as showing how a slight accident—powerless by itself to work mischief—may be very damaging when allied with so powerful an agent as running water.

Fig.92.

Fig.92.

The enduring character of even the roughest class of masonry arch, if only the material be good and abutments stable, is shown when it becomes necessary to destroy old work of this character.Fig. 92represents a short length of “cut and cover” arching in process of demolition, just before it fell in. The masonry was of hard sandstone rubble and had been cut away, as shown, till at the point A only a verysmall piece of the arch remained, when the length finally broke up and dropped. Arches have commonly a great reserve of strength; tunnel linings are, indeed, often badly out of shape, closed in, and sunken; yet continue, with close watching, and occasional repairs where the work has decayed or bulged, to serve the purpose intended.

Though the equilibrium of masonry arches has been the occasion of much profound study, and the nicest calculation has sometimes been applied to the design of such work, yet it appears that when an arch is well backed up, the theoretical linear arch need have but little connection with the figure of the intrados; a statement consonant both with common-sense and the teachings of experience. With solid backing, this would indeed seem to be more important than any part of the arch ring below the top of the backing, the lower part of the ring serving chiefly to preserve the face of the solid work. Arches are frequently to be met with so out of their true shape that but for the consideration named, failure would seem to be inevitable. The masonry or brickwork does not always show evidence of damage, if the distortion has been slow; suggesting that structures of this kind have a power of accommodation with which they are not generally credited.

A noticeable cause of deterioration of masonry structures, which may be quite independent of settlement, is serious vibration. This is well known in connection with church belfries, and is also locally apparent when telegraph or other poles are attached to masonry parapets. Vibration, when caused by heavy railway traffic, acting upon arches light or originally bad, may demoralise the structure to such an extent that repair becomes exceedingly difficult, because of the extensive character of the mischief; but masonry bridges substantially built, and particularly those carrying ordinary roads, and not subject to much vibration, have great lasting powers,if repaired with skill, or even let alone. Distortion of the arch may be quite consistent with practical stability, if the movement or decay with which it originated is not progressive, or has been arrested. In this connection a distinction is to be made between arches well backed, to which the foregoing remarks apply, and in which the two halves of each arch may act as separate monoliths meeting at the crown, and the case of a true arch ring independent of any outside resistance, such as backing or spandrels may give, and depending almost wholly upon the proper balance of its component voussoirs for its stability. With the latter class of structure no liberties may be taken; whilst with the former there is seldom cause for fear, if the foundations do not give way, and the work is dealt with judiciously, if at all. It must, however, be understood that there are limits as to what may be done effectively, short of rebuilding, in dealing with structures in which, perhaps, brickwork is rotten and mortar decayed and crumbling, the whole being little better than a broken mass of rubbish.

In cases where it may be prudent to introduce safety centring, as in an instance already referred to, it is commonly expedient to refrain from causing this to take any sensible part of the load till all movement has ceased, the centres being at the outset largely precautionary. The requirement with an arch in bad condition is to avoid disturbing it for the worse. If the centres are wedged up whilst movement is still going on, the effect may be to cause the arch to break up upon the centring, and precipitate repair work which might otherwise have been left to a more convenient time, when all movement had stopped or been checked by suitable measures. Viaduct arches in a bad condition, but not necessitating the use of relief centres, are commonly dealt with piecemeal by cutting out the bad places, a small partat a time, and making good. The work requires the greatest care of experienced men.

Pointing masonry or brickwork is effective for little other than protective purposes, and to check further weathering; it has obviously no effect upon the interior work, and if made to cover up the evidences of internal decay, is even misleading and objectionable. In extreme cases it may be desirable to open out the road and deal with the filling, to relieve or to strengthen the outer spandrel walls, which sometimes bulge, or for other purposes, as, for example, for rebuilding inner spandrel walls, grouting up or otherwise repairing solid backing, in which operations some regard must be had to the effect of the work upon the balance of the opposing halves of the arch.

Of the different classes of masonry commonly used in bridgework, it may be well to remark that good coursed rubble, or preferably that variety bonding both vertically and horizontally, of a durable stone, perhaps quite unfit for any but rough dressing, may make a most lasting structure, the mortar, of course, being good. Each rough-dressed stone presents a durable piece, fragments removed separate from the block, probably along some line of relative weakness—there is no “nursing” of weak corners; whereas with stones reduced to a perfectly regular shape by chisel work, the plane surfaces and geometrical angles are made with partial regard only to the natural grain of the stone.

The life of bridges of differing materials has been incidentally touched upon by the examples quoted, in dealing with each class of structure. It will be useful to recapitulate some of the facts adduced, and to compare the terms of life so far as they appear to be indicated; but in doing this it is necessary to remember that the life of a bridge of any one material is inseparably connected with its own private history. The duration of any such structure may be limited by adverse conditions, peculiar to the case considered, by defects of design, material, or workmanship—present from the first—or by neglect, overloading, or accident, making up its later record.

With the exception of timber structures, it is difficult to find any class of bridges furnishing examples which have reached the limit of life, independently of the evils named, and as a result of unavoidable decrepitude. There are none the less influences at work tending to this condition, and which it is too much to expect can in all cases be foreseen or completely guarded against, such as the shifting or scouring of river-beds, settlement of foundations, natural decay, and minor faults in design, which even in the most capable hands may be expected ever to fall short of perfection. At the best, then, the life of any structure, though long, must have a limit. With bridges of more average or inferior qualities the life may be positively short, even without the destructive influence of overloading.

Dealing with instances of metallic bridges, the adjacent table gives the time each had been in existence when removed, and some indication of the reason for its condemnation. Those marked with an asterisk were cases of pronounced high stress. From a study of the table it appears that in actual practice, making no excuses of any sort, the length of life of the wrought-iron bridges specified varied between twelve and thirty-six years; but these figures applied to this collection of cases only. It is to be remarked that many other bridges outlasted these, and are likely to continue reliable. These results show, then, no more than that some wrought-iron bridges are short-lived, having, in fact, been selected as examples of this. Longer-lived exceptions are useful, as indicating that the durability of such structures is by no means so limited as the table would suggest. It is to be observed that, as design and maintenance are now better and more generally understood than when experience was largely wanting, it is to be expected that later examples will show no such poor results.

Of steel bridges little can be said, because of the limited time this material has been in use; but the generally acknowledged belief, quite in agreement with the author’s observation, that steel rusts more freely than wrought iron, suggests that such bridges will have a shorter lease of life, the more so that the surface-to-section ratio is also greater for higher unit stresses, though other adverse influences are much the same for one material as for the other.

Of cast-iron structures but few cases have been given; of these, cast-iron arches have been noticed as developing defects which led to reconstruction, or to limiting the loads to be carried. Plain cast-iron girders, on the other hand, have never, under the author’s direct observation, been removed for any other reason than because they were cast iron, or from over-stress, due to the growth of loads; never fromdefects or wasting, though it is not suggested no such cases exist. The author has no evidence which points to what may be the limit of life of a good cast-iron girder fairly treated.

Examples of Life of Metallic Bridges.

With timber bridges the length of life appears to be about twenty-five years, but this is very largely dependent upon the question of maintenance, and may range from fifteen to thirty-five years. It is manifest that repairs, when extensive and consisting of the renewal of the more essential parts ofthe structure, border upon reconstruction, and may be continued indefinitely. The length of life in ordinary cases, and for the timbers commonly used in this country, may, for railway bridges, be taken as stated, though for highway bridges possibly longer.

Of masonry bridges little is to be said but that it is only in cases of bad work or material—with, perhaps, vibration or settlement—that these have a shortness of life comparable with that of defective metallic bridges. Where these adverse conditions obtain, heavy repairs may be necessary before the structure is many years old; but, under reasonably fair conditions, bridges of masonry may be expected to outlast structures in any other material. Apart from road-bridges which are admittedly long-lived, there are a large number of railway bridges and viaducts of masonry which, despite heavy loads and vibration, have been in use for the past seventy years.

Dealing with the cost of maintenance, this with bridges of wrought iron or steel should result simply from scraping and painting, with such other incidental work as may be necessary on the subsidiary materials used in the structure. The cost of painting will vary with the height and character of the bridge, and the amount of scaffolding, if any, and may be from 5d. to 1s. or more per square yard; this if distributed over five years, a not unusual interval between each painting, works out at an appreciable figure, which may vary from one-third to one per cent. of the first cost, per annum. The yearly cost of painting steel-work will, for shorter intervals, come to a somewhat higher figure. Serious occasional items of expense are those which should not be necessary, repairs and possibly strengthening, which may raise the total cost of maintenance very considerably.

Cast-iron bridges, being less liable to rust, cost less for painting than other metallic bridges; and if the cast iron is closed in by masonry, practically nothing; they do, indeed,involve very little expenditure in the maintenance. Not being very amenable to repair or strengthening, cast-iron bridges commonly remain very much as built, or are reconstructed.

The proper care of timber bridges may become costly as the structure gains in age, and soon grow to a very wasteful expenditure. This is evident when it is considered that repairs may be necessary after ten years, and that whatever may have been the cost of any part when new, it cannot be replaced for the same amount, having regard to the labour expended in removing the old member, and the special precautions to be observed in dealing with an old structure carrying its load. In addition to ordinary repairs, there will be paint or other protective coating to be applied, though this is not always done.

The upkeep charges of masonry bridges will be practically nothing in favourable cases; but, on the other hand, where extensive repairs become necessary, may reach a considerable amount. Exceptional outlays are, however, infrequent, and may be spread over a large number of years, in those rare instances in which they become imperative.

For purposes of ready comparison, placing bridges of the materials under review in order of durability, they would appear as in column 1 of the table above; in order of low maintenance charges, generally as in column 2; and in order of low first cost, as in column 3. With respect to the question of first cost, the arrangement of the third column applies only to small bridges, say, up to 70-foot span; and, beingliable to variation with the conditions, is but approximately correct. The less costly descriptions of masonry are alone considered in this connection.

It may be added that the total yearly charge of interest on first cost, redemption, and maintenance, appears to be for masonry bridges, about one-half only of the corresponding totals for bridges of wrought iron, steel, or timber; those of cast iron taking an intermediate place.

Summarising the above considerations, and dealing with the relative merits of bridges in the different materials, it may be broadly stated that for conditions at all suitable nothing seems to be superior to masonry—including in this description first-class brickwork—whether for road or railway bridges. One pronounced advantage of such bridges with respect to length of life, is that they are but little affected by increase of loads. The mass of a masonry arched structure is so great, and the margin of strength commonly so liberal, that considerable increments of load may have but little effect upon the reliability of the structure.

Cast iron has, for bridges of simple design, a strong claim to the second place, though its want of ductility is a demerit. It can, however, have but a limited use in bridge construction, being applicable only to small girder spans and skilfully-designed arched structures.

For bridges of moderate span in which the question of cost does not control the matter, wrought iron should probably come next, steel being best reserved for those of a larger size, in which weight of the structure greatly affects economy.

Timber may be regarded as a material rarely to be used in this country for structures to occupy a permanent place, unless for urgent economic reasons of the moment.

While expressing this general view of the matter, it is to be admitted that the propriety of these conclusions is somewhat discounted by the difficulty there now is in obtainingcast iron of the desired toughness, or wrought iron with promptitude and sufficient variety of section at a reasonable price.

It is apparent, also, that the choice of material may be largely influenced—even determined—by considerations of headway, construction depth, or character of foundations; so that no very definite rules can be usefully laid down, though the adoption of unsuitable materials has not been so unusual as to make these suggestions altogether purposeless.

The need for the reconstruction of bridges, arising from various causes which have been treated in the preceding chapters, original weakness or faults in design, decay or defects, may also be caused by such extraneous considerations as the growth of loads, widening of the openings spanned, or improvement of the headway.

In any case, a precise survey or measuring up of the structure and its immediate surroundings is required, in the execution of which the greatest care is desirable, and with respect to which it may be well to give a few hints.

The surveying chain, when used, should be tested, the measure of accuracy required rendering this imperative in a degree peculiar to work of this class. Linen tapes should also be compared with a reliable steel tape, and used only where sufficiently accurate for the particular purpose. A careful and observant man may do very good work with a linen tape, making just that allowance in the sag of the tape which corrects for the inevitable stretch; but there is still some uncertainty involved in its use, and the author prefers to rely upon a steel tape, notwithstanding the inconvenience commonly experienced from its intractable nature and liability to damage.

Instruments used must also be in the best adjustment; as errors, which in ordinary field work may not be of great importance, are inadmissible in bridge work.

It is not necessary here to enter upon the methods ofsmall survey work, but it may be desirable to point out that abutment walls should be plumbed for verticality; girders, which are liable to be leaning, defined in position by reference to their bearings; and generally that it should never be taken for granted that there is truth in old work, or that this may be assumed as to line or level.

In cases where disputes with any local authority as to headway are likely to arise, it is prudent to supplement the information as to level of soffits by rods cut to length in strict agreement with the clear height, before removing the old superstructure.

It is apparent that in cases where the superstructure is already condemned, the detail measurements may be confined to that part of the structure which is to remain, securing only such information as to the work superseded which may be required in arranging for the new work.

In taking particulars of skew bridges, needless as the warning may seem, it is yet necessary to remark that there may be right or left-hand skews which will not reverse. The author has known a disregard of this to make serious trouble in two instances.

Dealing first with reconstruction of the superstructure of railway under-bridges, these, if small, may not give much trouble, though the demand for greater strength will, perhaps, involve some difficulty in working to the limiting construction depth—i.e., the distance from the top of rail to soffit of bridge—particularly as many old bridges have a very niggardly allowance in this respect. It may be, and quite commonly is, necessary to raise the rails a small amount, or, if headway is not restricted, to lower the soffit. Clearances between the running gauge and girder-work may also be difficult to secure, more liberal allowances being now required than formerly. Complications in the character of the permanent way, so frequently found upon old bridges, should,of course, be got rid of, if possible; but the endeavour may introduce further difficulties. Regard must throughout be had to the methods to be adopted in removing old work and in erecting the new. Perhaps the simplest case to deal with is that where girders lie parallel to, and under the rails, with a timber floor upon which the permanent way is carried, as sections of the road involving pairs of girders may be readily removed, and replaced by the new girder-work (seeFig. 93). If the deck be of trough flooring or old rails, the matter may not be so simple, as regard must then be had to the position of joints in the existing floor, and the new work be schemed with respect to the number and office of girders which may be got in at any one breaking of the road. A slight slewing of rails may sometimes be resorted to on occasion, where this has the effect of releasing some part of the work not otherwise to be dealt with.


Back to IndexNext