Penalty.

57. Each case will contain the following:

One carpet renovator, with slot ¹⁄₄ in. by not less than 12 or more than 15 in. long.

One bare floor renovator, 15 in. long, with curved felt-covered face.

One wall brush, with skirted bristles, 12 in. long and ¹⁄₂ in. wide.

One hand brush, with hose connection at end, 8 in. long and 2 in. wide.

One 4-in. round brush for relief work.

One upholstery renovator.

One corner cleaner.

One radiator tool.

One curved stem about 5 ft. long.

One straight extension stem 5 ft. long.

At least one hat brush with the system.

58 to 64. Same as for Class 1.

64a. All brushes to be of substantial construction, with bestquality bristles set in close rows and as thick as possible, skirted with rubber, leather, or chamois skin, so that all air entering renovator will pass over surface being cleaned.

65 to 68. Same as for Class 1.

69.Hose Racks.Furnish and properly secure in place, where directed, .... hose racks in basement, .... each in first and second stories (.... racks in all). The racks to be constructed of cast-iron, galvanized or enamel finish, and each rack to be suitable for holding 75 ft. of hose of required size.

69a.Hose.There must be furnished with each hose rack, 75 ft. of non-collapsible hose in three 25-ft. lengths.

70. Hose shall not be less than 1 in. or more than 1-³⁄₄ in. inside diameter, best quality rubber hose, reinforced in best manner to absolutely prevent collapse at highest vacuum obtainable with the exhauster furnished and to prevent collapse if stepped on. Weight of hose to be not over 12 oz. per linear foot.

71 to 73. Same as for Class 1.

74. On completion of the plant, the pump will be operated with all outlets closed and under this condition the power consumption must not be more than 50% of that required under test conditions.

75. To test the capacity of plant, one hose line 100 ft. long shall be attached to inlet farthest from the separator, with standard vacometer with ¹⁄₂-in. opening in end of hose. Hose lines shall be attached to other outlets, each with 50-ft. hose and vacometer in end of hose, .... vacometers having ¹⁄₂-in. opening and .... vacometers having ⁷⁄₈-in. opening. Under these conditions 4 in. mercury must be maintained in vacometer at end of 100 ft. of hose.

75a.Test of Separators.At each of —— points, near —— outlets on different risers selected by the .... representative, the contractor shall furnish and spread on the floor, evenly covering an area of approximately 50 sq. ft. for each outlet, a mixture of 6 lbs. of dry sharp sand that will pass a 50-mesh screen, 3 lbs. of fine wheat flour, and 1 lb. of finely pulverized charcoal, if wet separator be used, and 6 lbs. of Portland cement, if bag be used.

75b. Fifty feet of hose of size required by the system usedshall be attached to each of the —— outlets, and the surface or surfaces prepared for cleaning shall be cleaned simultaneously by operators provided by the contractor until all of the sand, flour and charcoal has been taken up, when the exhauster shall be stopped and the dirt removed from the dry separator and spread on the floor again, and the operation of cleaning repeated until the mixture has been handled by the apparatus four times. If, after thoroughly flushing the system at completion of the above run, any dust or mud is found in the cylinder, ports, or valve chambers of the displacement exhauster, or if less than 95% of the dirt removed is found in the dry separator of the centrifugal exhauster, it shall be deemed sufficient ground for the rejection of the separators. If bag is used, same must not be disturbed until after capacity test, which will be made with material in separator after being picked up the fourth time.

76-77. Same as for Class 1.

78. Evaluation of proposal (for 4-sweeper plant): No proposal will be considered which contemplates furnishing an exhauster requiring more power to operate under test conditions than:

Full load, 14 K. W.; three-quarter load, 12.25 K. W.; one-half load, 10.5 K. W.

Test Requirement: Paragraph 75 to be considered full load. To reduce the load to three-quarters, one ⁷⁄₈-in. vacometer opening to be closed; to produce one-half load, one ¹⁄₂-in. opening to be closed in addition to the ⁷⁄₈-in. opening.

Bidders are requested to state in proposal the power consumption required by their apparatus at full, three-quarters and one-half loads, and in case the guarantees of the various bidders differ, they will be evaluated as follows for the purpose of comparison:

For each full K. W. of power consumption or fractional part thereof there will be allowed the following amount or proportionate parts for fractional parts of a K. W. hour at the various loads:

As an illustration, let it be assumed that proposals have been received offering equipment in accordance with specification requirements, and the one offering the most economical apparatus based on guaranteed power consumption names the highest price for the installation.

To determine if the purchaser will be justified in accepting the highest proposal, let it be assumed that he has guaranteed a power consumption of 1 K. W. less at full load, 0.75 K. W. less at three-quarters load, and 0.25 K. W. more at half-load than the lowest bidder. Under these conditions the algebraic sum of the saving of the higher bidder over the lower bidder would be 156 + 46.50 - 23.50 = 179, which is the additional amount in dollars which the purchaser would be warranted in paying for the apparatus of higher efficiency.

In making the economy test to determine if the guaranteed power consumption has been fulfilled, an integrating watt meter, previously calibrated and found correct, will be placed in circuit and a two-hour run made at each load and the power consumption based on the meter readings.

—It must be distinctly understood to be one of the conditions under which bids are to be submitted for the work embraced in this specification that the apparatus shall meet every requirement of the specification and the guaranty for efficiency under which conditions the contract price will be paid. In the event the apparatus tested fails to meet the specified requirements for capacity or economy, or both, the Architect shall have the right to reject the apparatus, absolutely, and require the installation of satisfactory apparatus, which shall comply with the contract requirements; or if he elects to accept the same, in the event the capacity or efficiency at any load (irrespective of other loads) is less than that named in the proposal, then the contract price shall be the amount named in the contract for a satisfactory plant, less the amount of deficiencies shown by the test based on the following:

—$500.00 for each inch of vacuum and a proportionate part thereof for each fraction of an inch below the 4 in. required in vacometer when operating under full load.

—Deduction for each K. W. or a proportionatepart thereof for each fraction thereof required in excess of guarantee.

This evaluation was based on the same time of operation and cost of current as that used in illustration under tests (Chapter XII).

The maximum power to be allowed for plants of various capacities should be as follows:

In event that the plant is to be run with vacuum “on tap,” as in a hotel, a guaranteed power consumption at no load should be required and evaluated on the number of hours the plant will probably operate under these conditions. This will be the largest item in the evaluation under such conditions.


Back to IndexNext